Skip links

CHEMICAL PLANT DEMOLITION

PDI was contracted to demolish 3 buildings. Our engineering team created a step-by-step plan to successfully demolish each of these structures safely. Starting with the smallest of the 3 buildings, PDI’s team used a method called “tripping” to selectively cut the taller structures down so that they fell in a controlled manner and in the proper direction. The materials from this project were sorted, processed, and then loaded onto rail cars and transported to recycling facilities.

Chemical Plant Demolition

PROJECT HIGHLIGHTS

This project was valued at $2M

Recycled Material: 90%

This project took place from October 2021 – December 2022

PDI IN ACTION

noun comment 106852

As part of our community engagement initiatives, PDI responded and made adjustments to production based on the neighbours’ concerns (with regard to dust) because of the number of excavators onsite (more than 12), and the high
volume of materials being processed every day (about 100 truckloads leaving the site each day).

RELATED PROJECTS

RETURN TO ALL PROJECTS