YONGE AND SOUDAN – 2161 YONGE ST DEMOLITION

Located in the middle of a densely populated urban setting, the demolition of 2161 Yonge St. in Toronto demanded the utmost in demolition engineering, technology, and equipment. At the Southeast corner of Yonge/Eglington, 2161 Yonge was a 9 storey post-tension building, which was immediately adjacent to a sidewalk, live traffic, and was nearly touching the neighboring buildings.

The main access road to the south, Sudan, was limited to one way traffic, so not to impede with the surrounding residential neighborhood. PDI performed a complete demolition and abatement of this structure, including all sidewalk protection, engineering, and the crushing of concrete material on site to act as backfill for future works. The demolition was performed in a top-down method, to not interfere with any existing traffic. PDI re-shored the existing structure, following the asbestos abatement and removal of interior finishes to allow smaller machines to sit on the top floor and hammer the existing structure.

PDI performed the demolition with no lost time injuries, worked ahead of the project schedule and diverted 98% of all materials from landfill. PDI received positive feedback from both the surrounding neighbours, and the customer for the cleanliness of the site, the speed of the demolition, and the limited disruption.

Yonge and Soudan

PROJECT HIGHLIGHTS

value

This project was valued at $2.797,383.80

recycle

Diverted 98% of all materials on site from landfill

start date

This project took place from April 2020 – February 2021

noun comment 106852

Managing risk for this project was mostly logistics based. The risks were identified and preventive measures were planned well in advance of the project’s start date.

Throughout the project ongoing communication was important for both the client and the neighbouring buildings. We addressed the issue of pedestrian traffic and indicated safety zones during structural demolition.