The 700ft Tansley Bridge was no small feat, with 3-truss girders, 4 spans at 48ft wide it carried two lanes of traffic and a sidewalk. The two outer spans (from abutment to pier) were 150ft long, the two center spans 200ft long. The highest point from the top of the roadway to the ground below was 105ft. Two excavators, one high reach, (3) elevated working platforms and (3) cranes were used to complete this project.
TANSLEY BRIDGE
PROJECT HIGHLIGHTS
Value
This project was valued at $900,000
Recycled Materials
Scrap metal (855 tons), Concrete rubble (87 triaxle loads) – 100% recycled
Project Timeline
This project took place from August 2023 – December 2023