AIRSIDE PAVEMENT RESTORATION PROGRAM

At the Toronto Pearson Airport, the PDI team was contracted to remove the existing concrete pavement to allow for new pavement to be constructed. Concrete was broken with a hydraulic hammer mounted to a 50T excavator. A second 50T excavator was used to excavate and load trucks for delivery to our onsite crushing operation and the remaining offsite. Concrete and cement stabilized base was 100% recycled. We crushed 75,000 tonnes to 37.5mm minus material and the remaining was crushed offsite. A third excavator was paired with a dozer to excavate and load the granular and sub grade material for offsite disposal.

Airside Pavement Restoration Program

PROJECT HIGHLIGHTS

value

Value

This project was valued at $3,087,437.36

recycle

Recycled Material

100% of the material from this job was recycled

start date

Project Timeline

This project took place from May 2020 – August 2020 and April 2022 – September 2022